ROUTE | Vatana, Thailand - BСC site, Russia.
CARGO | Chemical equipment
VOLUME | 7500 FT
IMPLEMENTATION PERIOD | June – August 2022
STAGE 1
It took more than 110 flights within 6 days to consolidate the entire cargo consignment in the port.
Works in the port and survey inspection were organized.
Projects for the placement and securing of cargo have been developed.
Supercargo was sent to the port to coordinate the work and the loading process.
STAGE 2
Chartering a suitable vessel
Loading cargo onto a ship using ship and terminal cranes
Organization of cargo securing in the hold
STAGE 3
Mooring of the vessel to the mooring wall in the port of Haydarpasa, Turkey.
Development of a plan for unloading and placing cargo at the site in the port
Unfastening the cargo and cleaning the hold
Mobilization of crane equipment.
Loading on two ships with Russian flags for delivery to the Port of St. Petersburg
STAGE 4
Mooring of the vessel to the mooring wall in the port of St. Petersburg
Development of a plan for unloading and placing cargo at the site in the port
Unfastening the cargo and cleaning the hold
Mobilization of crane equipment.
Loading on a car for delivery to the construction site